HPC & AI Factory — Land Acquisition Site Analysis

East Gdańsk 50–100 MW

A-tier. Excellent terrestrial fiber (Thinx Gdańsk, PIONIER, Atman metro). GUT workforce. Pomeranian SEZ. Nuclear plant planned ~80km (Choczewo). Nordic gateway positioning.

Site ID#2
Overall TierA
VoivodeshipPomorskie
Grid (DSO)Energa
Coordinates54.3326°N, 18.7383°E
RecommendationPROCEED — Grid Study + Energa Engagement
Overall TierA16-Factor Assessment
Power TierB50–100 MW
Fiber TierAAtman + HAWE
Composite3.45B+ — Weighted Score

Key Strengths

  • Thinx IX node IN Gdańsk — strong terrestrial fiber (corrected: no direct submarine landing)
  • PIONIER/TASK academic network + Atman metro ring
  • GUT (Gdańsk University of Technology) + Intel R&D presence = A-tier workforce
  • Pomeranian SEZ (PSEZ) active with DC-compatible zones
  • Cool Baltic climate — excellent PUE potential

Key Risks

  • Port zone land constraints — competing industrial/logistics demand
  • Coastal storm surge risk for low-elevation sites
  • Submarine cables land at Słupsk ~120km, NOT Gdańsk directly (corrected)
  • Energa less experienced with large DC grid connections vs Tauron
01

Power & Grid Infrastructure

WEIGHT: 25%
1
Power Availability
B
Port zone grid for heavy industry. Choczewo nuclear (~80km) transformative long-term. TBD for DC scale.
2
HV Grid Proximity
B
Standard Energa HV infrastructure. Port industrial zone has some capacity.
02

Connectivity & Fiber

WEIGHT: 15%
3
Fiber / Connectivity
A
CORRECTED: No submarine cable landing (Słupsk ~120km). But excellent terrestrial: Thinx, PIONIER/TASK, Atman metro.
4
Fiber Operators (Validated)
A
Orange, Exatel, HAWE, Atman metro ring. Thinx Gdańsk node confirmed.
03

Land & Infrastructure

WEIGHT: 20%
5
Land & Expansion
B
Port zone land available but constrained by competing logistics/industrial demand.
6
Transport Access
A
Port + A1 motorway + Lech Wałęsa Airport. Excellent multimodal transport.
7
Zoning / Permitting
B
Industrial zoning in port zone likely. May need specific DC permitting.
8
Scalability (>200MW)
B
Port zone limits large-scale expansion. Adequate for 50-100MW but not mega-campus.
04

Environment & Climate

WEIGHT: 15%
9
Water / Cooling
A
Vistula delta and Baltic coast. Excellent cooling water options.
10
Natural Disaster Risk
B
Coastal storm surge risk for low-elevation sites. No seismic but weather exposure.
11
Climate / PUE
S
Northern Poland Baltic coast — ~7-8.5°C avg. Among best PUE locations in Europe.
05

Economic & Workforce

WEIGHT: 25%
12
Workforce & Talent
A
GUT university, Intel R&D presence. Tri-City metro (Gdańsk-Sopot-Gdynia) ~750K.
13
SEZ / Tax Incentives
A
Pomeranian SEZ (PSEZ) active. Polish Investment Zone eligible.
14
Political Support
B
No deep relationships yet. City supportive of tech investment generally.
15
Market Proximity
B
Nordic/Scandinavian gateway. Baltic connectivity hub potential.
16
Land Cost
B
Port zone land pricing moderate. Not cheap (maritime premium) but not Warsaw-level.
06

Weighted Composite Score

Power & Grid — avg 3.00 × 0.250.75
Connectivity — avg 4.00 × 0.150.60
Land & Infrastructure — avg 3.25 × 0.200.65
Environment & Climate — avg 4.00 × 0.150.60
Economic & Regulatory — avg 3.40 × 0.250.85
COMPOSITE SCORE3.45 / 5.00 → B+
07

16-Factor Scoring Matrix

#FactorTierScoreCategory
1Power AvailabilityB3Power & Grid
2HV Grid ProximityB3Power & Grid
Power & Grid Average3.00× 0.25 = 0.75
3Fiber / ConnectivityA4Connectivity
4Fiber Operators (Validated)A4Connectivity
Connectivity Average4.00× 0.15 = 0.60
5Land & ExpansionB3Land & Infrastructure
6Transport AccessA4Land & Infrastructure
7Zoning / PermittingB3Land & Infrastructure
8Scalability (>200MW)B3Land & Infrastructure
Land & Infrastructure Average3.25× 0.20 = 0.65
9Water / CoolingA4Environment & Climate
10Natural Disaster RiskB3Environment & Climate
11Climate / PUES5Environment & Climate
Environment & Climate Average4.00× 0.15 = 0.60
12Workforce & TalentA4Economic & Regulatory
13SEZ / Tax IncentivesA4Economic & Regulatory
14Political SupportB3Economic & Regulatory
15Market ProximityB3Economic & Regulatory
16Land CostB3Economic & Regulatory
Economic & Regulatory Average3.40× 0.25 = 0.85
COMPOSITE TOTAL3.45B+ — PROCEED
08

Location Data

Coordinates54.3326°N, 18.7383°E
Google MapsOpen in Maps →
VoivodeshipPomorskie
Grid DSOEnerga
Fiber PrimaryAtman + HAWE
Power ConfirmedTBD — Port zone grid capacity
09

CEE Portfolio Context

CountryTierCapacityStatus
🇵🇱PolandS2 GW+Phase 1 under construction. 20 sites assessed. Stargard (S-tier) primary.
🇷🇴RomaniaA369 MWAvram Iancu — 369MW PV+BESS co-location. Grid-connected. In planning.
🇧🇬BulgariaA1 GWIn planning. Kozloduy nuclear corridor. Strong grid.
🇨🇿Czech RepublicB+200 MWUp next. Prague metro + industrial zones. NIX.CZ IXP.
🇪🇪EstoniaB+100 MWUp next. Tallinn data hub. Cool climate. Nordic connectivity.
🇭🇺HungaryB150 MWBudapest metro. BIX IXP. Paks nuclear proximity. Evaluate.
🇱🇹LithuaniaB100 MWVilnius/Kaunas. LINX node. Baltic interconnection. Evaluate.
🇱🇻Latvia / SlovakiaB–50 MWEarly evaluation. Riga / Bratislava metro areas.
🇭🇷Croatia / SloveniaC50 MWEvaluate. Zagreb / Ljubljana. Limited grid. Emerging markets.
🇷🇸Serbia, BiH, OthersDMonitor only. Regulatory uncertainty. Grid instability.

Strategic Recommendation

PROCEED — Grid Study + Energa Engagement

Commission Energa grid study for port zone capacity. Strong fiber hub with Thinx Gdańsk IXP. GUT university provides talent. Choczewo nuclear plant (~80km) transformative long-term. Position as Nordic/Scandinavian gateway. Watch: submarine cables land at Słupsk ~120km, not Gdańsk directly.