HPC & AI Factory — Land Acquisition Site Analysis

Kobierzyce 50 MW

A-tier. ⚡ POWERED+PERMITTED per Filip — PENDING KOS CONFIRMATION. 50MW Tier 1, ~500MW total portfolio. Identical fiber to Site #4 (Bielany).

Site ID#11
Overall TierA
VoivodeshipDolnośląskie
Grid (DSO)Tauron
Coordinates51.0339°N, 16.8725°E
RecommendationPROCEED — ⚡ Confirm KOS First (Filip Option)
Overall TierA16-Factor Assessment
Power TierB+50 MW
Fiber TierAAtman + WRIX
Composite3.9A — Weighted Score

Key Strengths

  • ⚡ POWERED+PERMITTED per Filip — 50MW ready (PENDING KOS confirmation)
  • WRIX + Thinx <15km — same excellent fiber as Wrocław Bielany (#4)
  • LG Chem, Prologis adjacent — confirms HV industrial grid exists
  • Wrocław metro S-tier workforce (640K)

Key Risks

  • Grid KOS study needed — 50MW based on Filip's representation, not independently confirmed
  • 50MW facility smaller scale — not a mega-campus
  • Filip option deal complexity — double-dip compensation structure
  • Land-in-kind arrangement adds legal/structural complexity
01

Power & Grid Infrastructure

WEIGHT: 25%
1
Power Availability
A
⚡ 50MW per Filip representation. PENDING Tauron KOS confirmation. Grid access claimed available.
2
HV Grid Proximity
A
LG Chem (2km S), Prologis adjacent — confirms HV industrial grid exists in area.
02

Connectivity & Fiber

WEIGHT: 15%
3
Fiber / Connectivity
A
Same zone as Site #4. WRIX (5 DCs) + Thinx within 15km. Excellent.
4
Fiber Operators (Validated)
A
Orange (A4/A8), Exatel, HAWE (~55km), Atman metro. WRIX+Thinx in range.
03

Land & Infrastructure

WEIGHT: 20%
5
Land & Expansion
B
Specific Kobierzyce commune plot. Permitted but limited expansion potential.
6
Transport Access
S
A4/A8 junction. Wrocław airport proximity. Excellent logistics.
7
Zoning / Permitting
S
⚡ PERMITTED — Industrial MPZP in place per Filip. No conversion needed.
8
Scalability (>200MW)
C
50MW single site. Not a mega-campus. Filip portfolio = ~500MW total but spread across sites.
04

Environment & Climate

WEIGHT: 15%
9
Water / Cooling
A
Wrocław metro municipal water. Adequate for 50MW facility.
10
Natural Disaster Risk
A
Low risk. Kobierzyce commune elevated. Not in major flood zone.
11
Climate / PUE
A
Lower Silesian climate. Good PUE conditions.
05

Economic & Workforce

WEIGHT: 25%
12
Workforce & Talent
S
Wrocław metro 640K. PWr university. Poland's #3 tech hub.
13
SEZ / Tax Incentives
A
Polish Investment Zone eligible. Industrial corridor.
14
Political Support
C
Via Filip — no direct municipality relationship.
15
Market Proximity
A
Wrocław metro. DACH corridor. Same market position as Site #4.
16
Land Cost
A
Via Filip option — pre-agreed discounted pricing. PLN 180-300/sqm base.
06

Weighted Composite Score

Power & Grid — avg 4.00 × 0.251.00
Connectivity — avg 4.00 × 0.150.60
Land & Infrastructure — avg 3.75 × 0.200.75
Environment & Climate — avg 4.00 × 0.150.60
Economic & Regulatory — avg 3.80 × 0.250.95
COMPOSITE SCORE3.9 / 5.00 → A
07

16-Factor Scoring Matrix

#FactorTierScoreCategory
1Power AvailabilityA4Power & Grid
2HV Grid ProximityA4Power & Grid
Power & Grid Average4.00× 0.25 = 1.00
3Fiber / ConnectivityA4Connectivity
4Fiber Operators (Validated)A4Connectivity
Connectivity Average4.00× 0.15 = 0.60
5Land & ExpansionB3Land & Infrastructure
6Transport AccessS5Land & Infrastructure
7Zoning / PermittingS5Land & Infrastructure
8Scalability (>200MW)C2Land & Infrastructure
Land & Infrastructure Average3.75× 0.20 = 0.75
9Water / CoolingA4Environment & Climate
10Natural Disaster RiskA4Environment & Climate
11Climate / PUEA4Environment & Climate
Environment & Climate Average4.00× 0.15 = 0.60
12Workforce & TalentS5Economic & Regulatory
13SEZ / Tax IncentivesA4Economic & Regulatory
14Political SupportC2Economic & Regulatory
15Market ProximityA4Economic & Regulatory
16Land CostA4Economic & Regulatory
Economic & Regulatory Average3.80× 0.25 = 0.95
COMPOSITE TOTAL3.9A — PROCEED
08

Location Data

Coordinates51.0339°N, 16.8725°E
Google MapsOpen in Maps →
VoivodeshipDolnośląskie
Grid DSOTauron
Fiber PrimaryAtman + WRIX
Power Confirmed50 MW per Filip — ⚡ PENDING KOS CONFIRMATION
09

CEE Portfolio Context

CountryTierCapacityStatus
🇵🇱PolandS2 GW+Phase 1 under construction. 20 sites assessed. Stargard (S-tier) primary.
🇷🇴RomaniaA369 MWAvram Iancu — 369MW PV+BESS co-location. Grid-connected. In planning.
🇧🇬BulgariaA1 GWIn planning. Kozloduy nuclear corridor. Strong grid.
🇨🇿Czech RepublicB+200 MWUp next. Prague metro + industrial zones. NIX.CZ IXP.
🇪🇪EstoniaB+100 MWUp next. Tallinn data hub. Cool climate. Nordic connectivity.
🇭🇺HungaryB150 MWBudapest metro. BIX IXP. Paks nuclear proximity. Evaluate.
🇱🇹LithuaniaB100 MWVilnius/Kaunas. LINX node. Baltic interconnection. Evaluate.
🇱🇻Latvia / SlovakiaB–50 MWEarly evaluation. Riga / Bratislava metro areas.
🇭🇷Croatia / SloveniaC50 MWEvaluate. Zagreb / Ljubljana. Limited grid. Emerging markets.
🇷🇸Serbia, BiH, OthersDMonitor only. Regulatory uncertainty. Grid instability.

Strategic Recommendation

PROCEED — ⚡ Confirm KOS First (Filip Option)

A-tier with ⚡ potential Tier 1 asset. 50MW powered+permitted per Filip's representation — MUST CONFIRM via Tauron KOS study. If KOS confirms: shovel-ready 6-12 months, crown jewel of Filip option portfolio. If KOS fails: drops to Tier 2 timeline (12-24mo). Same Wrocław metro fiber as Site #4. See Filip Option Valuation for deal structure analysis.