A-tier MAJOR OPPORTUNITY. 400ha LSSE park, fully serviced — originally Intel's $4.6B fab site (cancelled). 245M PLN infrastructure invested. Wrocław metro workforce. WRIX+Thinx <25km.
| # | Factor | Tier | Score | Category |
|---|---|---|---|---|
| 1 | Power Availability | B+ | 3.5 | Power & Grid |
| 2 | HV Grid Proximity | B+ | 3.5 | Power & Grid |
| Power & Grid Average | 3.50 | × 0.25 = 0.88 | ||
| 3 | Fiber / Connectivity | A | 4 | Connectivity |
| 4 | Fiber Operators (Validated) | A | 4 | Connectivity |
| Connectivity Average | 4.00 | × 0.15 = 0.60 | ||
| 5 | Land & Expansion | S | 5 | Land & Infrastructure |
| 6 | Transport Access | A | 4 | Land & Infrastructure |
| 7 | Zoning / Permitting | A | 4 | Land & Infrastructure |
| 8 | Scalability (>200MW) | S | 5 | Land & Infrastructure |
| Land & Infrastructure Average | 4.50 | × 0.20 = 0.90 | ||
| 9 | Water / Cooling | A | 4 | Environment & Climate |
| 10 | Natural Disaster Risk | C | 2 | Environment & Climate |
| 11 | Climate / PUE | A | 4 | Environment & Climate |
| Environment & Climate Average | 3.33 | × 0.15 = 0.50 | ||
| 12 | Workforce & Talent | S | 5 | Economic & Regulatory |
| 13 | SEZ / Tax Incentives | S | 5 | Economic & Regulatory |
| 14 | Political Support | A | 4 | Economic & Regulatory |
| 15 | Market Proximity | A | 4 | Economic & Regulatory |
| 16 | Land Cost | A | 4 | Economic & Regulatory |
| Economic & Regulatory Average | 4.40 | × 0.25 = 1.10 | ||
| COMPOSITE TOTAL | 3.98 | A — PROCEED |
| Country | Tier | Capacity | Status | |
|---|---|---|---|---|
| 🇵🇱 | Poland | S | 2 GW+ | Phase 1 under construction. 20 sites assessed. Stargard (S-tier) primary. |
| 🇷🇴 | Romania | A | 369 MW | Avram Iancu — 369MW PV+BESS co-location. Grid-connected. In planning. |
| 🇧🇬 | Bulgaria | A | 1 GW | In planning. Kozloduy nuclear corridor. Strong grid. |
| 🇨🇿 | Czech Republic | B+ | 200 MW | Up next. Prague metro + industrial zones. NIX.CZ IXP. |
| 🇪🇪 | Estonia | B+ | 100 MW | Up next. Tallinn data hub. Cool climate. Nordic connectivity. |
| 🇭🇺 | Hungary | B | 150 MW | Budapest metro. BIX IXP. Paks nuclear proximity. Evaluate. |
| 🇱🇹 | Lithuania | B | 100 MW | Vilnius/Kaunas. LINX node. Baltic interconnection. Evaluate. |
| 🇱🇻 | Latvia / Slovakia | B– | 50 MW | Early evaluation. Riga / Bratislava metro areas. |
| 🇭🇷 | Croatia / Slovenia | C | 50 MW | Evaluate. Zagreb / Ljubljana. Limited grid. Emerging markets. |
| 🇷🇸 | Serbia, BiH, Others | D | — | Monitor only. Regulatory uncertainty. Grid instability. |
PROCEED — Critical Opportunity (Ex-Intel Site)
A-tier MAJOR OPPORTUNITY. 400ha industrial park in LSSE, fully serviced (roads, water, wastewater) — originally prepared for Intel's $4.6B semiconductor fab (cancelled). 245M PLN infrastructure already invested by municipality. Ready for large-scale tenant. Contact LSSE/Miękinia immediately for available plots + grid capacity post-Intel. BUT: confirm grid capacity post-withdrawal + Odra flood risk assessment needed.