HPC & AI Factory — Land Acquisition Site Analysis

Stargard Industrial Park 480 MW → 1 GW+

S-tier moat: Pre-cleared DC zoning, 480MW phased allocation, Delta 41yr partnership, City President aligned. Amsterdam fiber 5km. No other site replicates this combination.

Site ID★ Primary
Overall TierS
VoivodeshipZachodniopomorskie
Grid (DSO)ENEA
Coordinates53.335°N, 15.05°E
RecommendationEXECUTE — Immediate Priority
Overall TierS16-Factor Assessment
Power TierA480 MW → 1 GW+
Fiber TierAHAWE + Exatel
Composite4.33A+ — Weighted Score

Key Strengths

  • 480MW ENEA phased power allocation (80+80+160+160MW) with PSE 1GW pending
  • 1,800ha industrial park with pre-cleared data center zoning — unique in Poland
  • Delta 41-year partnership and City President political alignment
  • Amsterdam fiber trunk 5km via HAWE backbone — international connectivity
  • SEZ tax incentives confirmed with DC-specific zoning plan

Key Risks

  • Small workforce base (70K city) — will need regional recruitment
  • No local IXP — nearest Thinx Szczecin ~60km
  • Single DSO dependency (ENEA) for all power phases
01

Power & Grid Infrastructure

WEIGHT: 25%
1
Power Availability
A
480MW ENEA phased (80+80+160+160). PSE 1GW pending. Clear path to multi-GW campus.
2
HV Grid Proximity
S
On-site 100kV substation within Stargard Industrial Park. Direct ENEA connection.
02

Connectivity & Fiber

WEIGHT: 15%
3
Fiber / Connectivity
A
Amsterdam fiber trunk 5km (HAWE backbone). Exatel 21,800km ring covers region. Corrected from S: no LOCAL IXP.
4
Fiber Operators (Validated)
A
HAWE backbone + Exatel ring. Orange. No Atman/Thinx locally but Amsterdam trunk is key asset.
03

Land & Infrastructure

WEIGHT: 20%
5
Land & Expansion
S
1,800ha industrial park — unmatched in Poland. Pre-cleared DC zoning. Room for multi-GW campus.
6
Transport Access
A
S10/S3 expressway junction. Szczecin port 60km. Rail connection available.
7
Zoning / Permitting
S
Pre-cleared for data center in spatial plan. No conversion needed. Shovel-ready.
8
Scalability (>200MW)
S
480MW phased + PSE 1GW pending + 1,800ha park. Multi-GW campus potential.
04

Environment & Climate

WEIGHT: 15%
9
Water / Cooling
A
Adequate water supply via municipal and Ina river system. No major constraints identified.
10
Natural Disaster Risk
A
Low natural disaster risk. Not in flood zone. No seismic activity. No mining subsidence.
11
Climate / PUE
S
Northern Poland ~7-8°C annual avg. Excellent PUE potential. Among best in continental Europe.
05

Economic & Workforce

WEIGHT: 25%
12
Workforce & Talent
B
70K city — small but Szczecin metro (400K+) 60km provides talent pool. Will need bus/shuttle program.
13
SEZ / Tax Incentives
S
SEZ confirmed with DC-specific zoning plan. Polish Investment Zone eligible. Unique municipal support.
14
Political Support
S
Deep relationship built — City President, Park Director, heat reuse plan. 41-year Delta partnership.
15
Market Proximity
B
Not a primary market hub but positioned for DACH/Nordic routes via Szczecin/Berlin corridor.
16
Land Cost
A
Good municipal pricing within industrial park. Below Wrocław/Warsaw premium levels.
06

Weighted Composite Score

Power & Grid — avg 4.50 × 0.251.12
Connectivity — avg 4.00 × 0.150.60
Land & Infrastructure — avg 4.75 × 0.200.95
Environment & Climate — avg 4.33 × 0.150.65
Economic & Regulatory — avg 4.00 × 0.251.00
COMPOSITE SCORE4.33 / 5.00 → A+
07

16-Factor Scoring Matrix

#FactorTierScoreCategory
1Power AvailabilityA4Power & Grid
2HV Grid ProximityS5Power & Grid
Power & Grid Average4.50× 0.25 = 1.12
3Fiber / ConnectivityA4Connectivity
4Fiber Operators (Validated)A4Connectivity
Connectivity Average4.00× 0.15 = 0.60
5Land & ExpansionS5Land & Infrastructure
6Transport AccessA4Land & Infrastructure
7Zoning / PermittingS5Land & Infrastructure
8Scalability (>200MW)S5Land & Infrastructure
Land & Infrastructure Average4.75× 0.20 = 0.95
9Water / CoolingA4Environment & Climate
10Natural Disaster RiskA4Environment & Climate
11Climate / PUES5Environment & Climate
Environment & Climate Average4.33× 0.15 = 0.65
12Workforce & TalentB3Economic & Regulatory
13SEZ / Tax IncentivesS5Economic & Regulatory
14Political SupportS5Economic & Regulatory
15Market ProximityB3Economic & Regulatory
16Land CostA4Economic & Regulatory
Economic & Regulatory Average4.00× 0.25 = 1.00
COMPOSITE TOTAL4.33A+ — EXECUTE
08

Location Data

Coordinates53.335°N, 15.05°E
Google MapsOpen in Maps →
VoivodeshipZachodniopomorskie
Grid DSOENEA
Fiber PrimaryHAWE + Exatel
Power Confirmed90 MW confirmed (80+80+160+160 phased)
09

CEE Portfolio Context

CountryTierCapacityStatus
🇵🇱PolandS2 GW+Phase 1 under construction. 20 sites assessed. Stargard (S-tier) primary.
🇷🇴RomaniaA369 MWAvram Iancu — 369MW PV+BESS co-location. Grid-connected. In planning.
🇧🇬BulgariaA1 GWIn planning. Kozloduy nuclear corridor. Strong grid.
🇨🇿Czech RepublicB+200 MWUp next. Prague metro + industrial zones. NIX.CZ IXP.
🇪🇪EstoniaB+100 MWUp next. Tallinn data hub. Cool climate. Nordic connectivity.
🇭🇺HungaryB150 MWBudapest metro. BIX IXP. Paks nuclear proximity. Evaluate.
🇱🇹LithuaniaB100 MWVilnius/Kaunas. LINX node. Baltic interconnection. Evaluate.
🇱🇻Latvia / SlovakiaB–50 MWEarly evaluation. Riga / Bratislava metro areas.
🇭🇷Croatia / SloveniaC50 MWEvaluate. Zagreb / Ljubljana. Limited grid. Emerging markets.
🇷🇸Serbia, BiH, OthersDMonitor only. Regulatory uncertainty. Grid instability.

Strategic Recommendation

EXECUTE — Immediate Priority

S-tier primary site. Execute first. 480MW ENEA phased allocation with PSE 1GW pending. Pre-cleared DC zoning in Stargard Industrial Park (1,800ha). Deep political relationships built. Delta 41-year partnership in place. Q1 2027 target go-live. All other sites are expansion candidates around this anchor.