HPC & AI Factory — Land Acquisition Site Analysis

Wałbrzych 30–80 MW

B-tier. WSEZ INVEST-PARK is Poland's largest SEZ operator (2,212ha, 41 subzones) but city in demographic decline. Weak grid. Better for light industrial than 160MW AI factory.

Site ID#18
Overall TierB
VoivodeshipDolnośląskie
Grid (DSO)Tauron
Coordinates50.80793°N, 16.311676°E
RecommendationCONDITIONAL — Low Priority, SEZ Incentives Only
Overall TierB16-Factor Assessment
Power TierC30–80 MW
Fiber TierBHAWE + Exatel
Composite2.9B — Weighted Score

Key Strengths

  • WSEZ INVEST-PARK — Poland's largest SEZ operator (2,212ha, 41 subzones)
  • Strong SEZ tax incentives available
  • HAWE HQ Legnica ~50km for fiber
  • Czech/German border proximity — cross-border market angle

Key Risks

  • City in demographic decline (110K, formerly 140K)
  • Weak power grid — post-mining, mountainous terrain
  • No IXP locally — WRIX Wrocław ~75km
  • Mountainous Lower Silesian terrain complicates large-scale infrastructure
01

Power & Grid Infrastructure

WEIGHT: 25%
1
Power Availability
C
Post-mining city. Tauron grid but no confirmed HV for DC scale. Mountainous terrain complicates.
2
HV Grid Proximity
C
Standard Tauron distribution. No large substation for DC scale confirmed.
02

Connectivity & Fiber

WEIGHT: 15%
3
Fiber / Connectivity
B
HAWE HQ Legnica ~50km. WRIX Wrocław ~75km. No local IXP. Adequate for training.
4
Fiber Operators (Validated)
B
HAWE (~50km), Exatel ring, Orange. Adequate backbone but no local IXP.
03

Land & Infrastructure

WEIGHT: 20%
5
Land & Expansion
C
SEZ plots available but mountainous terrain limits large flat sites.
6
Transport Access
B
S3/S8 access. Czech border. Mountainous roads.
7
Zoning / Permitting
B
SEZ plots have industrial zoning. Standard permitting.
8
Scalability (>200MW)
C
Limited by grid, terrain, and workforce. Not suitable for mega-campus.
04

Environment & Climate

WEIGHT: 15%
9
Water / Cooling
B
Mountain water sources. Adequate but terrain adds complexity.
10
Natural Disaster Risk
A
Mountainous — good drainage. Not in major flood zone. Low seismic.
11
Climate / PUE
A
Mountain climate — cooler than lowlands. Good PUE potential.
05

Economic & Workforce

WEIGHT: 25%
12
Workforce & Talent
C
110K declining city. Post-mining economy. No major university.
13
SEZ / Tax Incentives
S
WSEZ INVEST-PARK — Poland's largest SEZ. 2,212ha, 41 subzones. Very strong incentives.
14
Political Support
B
SEZ administration active. City seeking post-mining investment.
15
Market Proximity
B
Czech/German border. Moderate market proximity.
16
Land Cost
S
Post-mining, declining city. Very cheap land. SEZ pricing favorable.
06

Weighted Composite Score

Power & Grid — avg 2.00 × 0.250.50
Connectivity — avg 3.00 × 0.150.45
Land & Infrastructure — avg 2.50 × 0.200.50
Environment & Climate — avg 3.67 × 0.150.55
Economic & Regulatory — avg 3.60 × 0.250.90
COMPOSITE SCORE2.9 / 5.00 → B
07

16-Factor Scoring Matrix

#FactorTierScoreCategory
1Power AvailabilityC2Power & Grid
2HV Grid ProximityC2Power & Grid
Power & Grid Average2.00× 0.25 = 0.50
3Fiber / ConnectivityB3Connectivity
4Fiber Operators (Validated)B3Connectivity
Connectivity Average3.00× 0.15 = 0.45
5Land & ExpansionC2Land & Infrastructure
6Transport AccessB3Land & Infrastructure
7Zoning / PermittingB3Land & Infrastructure
8Scalability (>200MW)C2Land & Infrastructure
Land & Infrastructure Average2.50× 0.20 = 0.50
9Water / CoolingB3Environment & Climate
10Natural Disaster RiskA4Environment & Climate
11Climate / PUEA4Environment & Climate
Environment & Climate Average3.67× 0.15 = 0.55
12Workforce & TalentC2Economic & Regulatory
13SEZ / Tax IncentivesS5Economic & Regulatory
14Political SupportB3Economic & Regulatory
15Market ProximityB3Economic & Regulatory
16Land CostS5Economic & Regulatory
Economic & Regulatory Average3.60× 0.25 = 0.90
COMPOSITE TOTAL2.9B — CONDITIONAL
08

Location Data

Coordinates50.80793°N, 16.311676°E
Google MapsOpen in Maps →
VoivodeshipDolnośląskie
Grid DSOTauron
Fiber PrimaryHAWE + Exatel
Power ConfirmedTBD — Weak grid, post-mining
09

CEE Portfolio Context

CountryTierCapacityStatus
🇵🇱PolandS2 GW+Phase 1 under construction. 20 sites assessed. Stargard (S-tier) primary.
🇷🇴RomaniaA369 MWAvram Iancu — 369MW PV+BESS co-location. Grid-connected. In planning.
🇧🇬BulgariaA1 GWIn planning. Kozloduy nuclear corridor. Strong grid.
🇨🇿Czech RepublicB+200 MWUp next. Prague metro + industrial zones. NIX.CZ IXP.
🇪🇪EstoniaB+100 MWUp next. Tallinn data hub. Cool climate. Nordic connectivity.
🇭🇺HungaryB150 MWBudapest metro. BIX IXP. Paks nuclear proximity. Evaluate.
🇱🇹LithuaniaB100 MWVilnius/Kaunas. LINX node. Baltic interconnection. Evaluate.
🇱🇻Latvia / SlovakiaB–50 MWEarly evaluation. Riga / Bratislava metro areas.
🇭🇷Croatia / SloveniaC50 MWEvaluate. Zagreb / Ljubljana. Limited grid. Emerging markets.
🇷🇸Serbia, BiH, OthersDMonitor only. Regulatory uncertainty. Grid instability.

Strategic Recommendation

CONDITIONAL — Low Priority, SEZ Incentives Only

B-tier. Wałbrzych SEZ (INVEST-PARK) is Poland's largest SEZ operator — strong incentives. But city in demographic decline (110K → declining), weak power grid, no local IXP (WRIX Wrocław ~75km), mountainous terrain. Better suited for light industrial than 160MW AI factory. Consider only for small-scale (<50MW) edge facility if SEZ terms are exceptional.